Maintenance of a road-rail vehicle aims to keep it, or return it, to a good condition; it does not replace VGP, the pre-use check or rail compliance. Good tracking starts from the real machine (configuration, meters, service plan), keeps each maintenance order alive until the evidence is in, and uses history to make decisions.
Organise road-rail equipment maintenance: plan, jobs, hour meters, findings and traceability without confusing it with VGP.
Starting point
Distinguishing maintenance, VGP, pre-use checks and compliance
Preventive or corrective maintenance aims to keep or restore the machine to a defined state. A periodic general inspection (VGP) looks, under the applicable framework, for deterioration likely to create a hazard. The pre-use check serves a different purpose: it helps the operator detect a visible fault or a change that has occurred since the last use. Lastly, the compliance file covers, among other things, design, placing on the market or into service, and the machine's configuration.
These layers complement one another without replacing each other. A favourable VGP report does not on its own prove that all the operations required by the manufacturer have been carried out. Up-to-date maintenance does not amount to an operator authorisation, admission of a machine onto a network, or approval for a given site. The manager's first task is therefore to define each requirement and who is responsible for it.
| Record | Question addressed | Example of evidence |
|---|---|---|
| Maintenance | Has the planned or necessary technical operation been carried out? | Work order, reading, parts replaced, signature |
| Inspection | Has the required check been carried out, and with what result? | Report, date, findings and the inspector's identity |
| Pre-use | Does the machine show a fault or anomaly before the mission? | Dated checklist and reported anomaly |
| Network or site | Are the local conditions for deployment met? | Authorisation, restriction, instruction or file requested |
Structure
Building the reference plan from the real machine
The plan must start from the serial number, the model, the year, the base machine and the rail equipment actually fitted. Lifting accessories, tools, limiters, braking devices or other sub-assemblies may have their own instructions and checks. Copying the plan of a similar machine without checking its configuration creates misleading deadlines.
Manufacturer's manuals, earlier reports, employer requirements, risk assessment results and client requirements feed this reference plan. A frequency must not be invented because it seems common. It must be linked to an identifiable source and reassessed after a modification, an incident, a return to service or a long period out of use.
Working checklist
- ✓ Identify machine, chassis, rail components, tools and accessories unambiguously.
- ✓ Link each operation to its source, its interval and the competence required.
- ✓ Distinguish hour meter, mileage, calendar date and triggering event.
- ✓ Keep track of manual and plan versions applied over time.
No universal regime for all road-rail equipment
The relevant checks and documents depend in particular on the function, the equipment, the context of use and the applicable rules. The term “road-rail equipment” alone does not allow a complete list or frequency to be inferred.
Execution
Keeping a maintenance order alive from opening to proof
A useful deadline triggers an action, not just an alert. The work order describes the machine, the expected operation, instructions, the parts or measures needed and the urgency level. On return, the technician records what was actually done, the values observed, the components replaced, any discrepancies and the date the machine was returned to service.
- 1. Trigger Create the job from a date, a meter reading, a reported fault or a defined event.
- 2. Carry out and document Record the operations, readings, parts, useful photos and the people actually involved.
- 3. Decide Formalise return to service, a restriction, a further check or immobilisation.
- 4. Close Close only once the evidence and the treatment of findings are linked to the right machine.
Inspections
Tracking a VGP without turning it into a simple green light
The French ministerial orders of 1 March 2004 and 5 March 1993 (arrêtés du 1er mars 2004 et du 5 mars 1993) set out inspections for defined categories of equipment. Their applicability to a machine or an accessory must be checked against its function and equipment. The report must remain viewable in full: date, scope, conditions of the inspection, result, observations and findings give meaning to the deadline displayed.
A finding is not cleared by downloading a more recent report. It must be linked to an action, a decision and, where necessary, proof of closure. In the case of hire, documentary and operational responsibilities must be clarified between the rental company, the user and those involved, without assuming that a document handed over at delivery covers the whole period of use.
- Show the report's date and scope, not just a calculated expiry date.
- Keep the original file and the exact identity of the equipment examined.
- Link each observation to its treatment, its priority and its proof of closure.
- Re-examine the file after a modification, accident, major repair or change of use.
Fleet oversight
Turning history into operational decisions
A relevant dashboard separates operations to be scheduled, overdue jobs, missing reports, open findings and immobilised machines. It must allow a return to the source document. The completion rate alone is not enough if the work is poorly linked, if readings are missing or if faults recur.
Trackary can centralise dates, documents, meters, jobs and history around each machine. This organisation makes it easier to chase things up and prepare a file, but it does not determine the applicable regime, does not carry out the inspection and does not guarantee compliance. Validation remains the responsibility of the competent people and bodies.
The software organises the record
The quality of the tracking depends on the reference plan, the data entered and human checks. Trackary does not replace legal analysis, the manual or technical expertise.
Frequently asked questions
Sources and limits of this guide
- INRS ED 6339 — Regulatory inspections of machines ↗ Pointers on the purpose of inspections and maintenance.
- INRS — Periodic inspections of work equipment ↗ Employer obligations and scope of checks.
- Légifrance — French ministerial order of 1 March 2004 (arrêté du 1er mars 2004) ↗ Inspections of lifting appliances and accessories.
- Légifrance — French ministerial order of 5 March 1993 (arrêté du 5 mars 1993) ↗ Periodic general inspection of certain work equipment.
- SNCF Réseau — Checking the compliance of works equipment ↗ Process presented for works equipment.
- General guide, without legal qualification for any particular case.
- Manuals, consolidated texts, network rules, site requirements and the decisions of competent people take precedence.
- Trackary keeps and links information; it does not carry out VGP inspections, maintenance or authorisation to return to service.