Preventive maintenance

What is a preventive maintenance plan?

In brief

A preventive maintenance plan is the list, machine by machine, of the upkeep to carry out before a breakdown: which task, at what interval (every X hours or every X months), who does it and when it was last done. For an equipment fleet, it is based on the manufacturer’s manual and hour meters. Download our free Excel template to build one.

Preventive maintenance means acting before a machine breaks down. But you still need to know what to do, when, and on which machine. That is the role of the preventive maintenance plan. Here is how to build one simply, with a ready-to-fill Excel template.

Preventive maintenance: a simple definition

Preventive maintenance covers all work carried out before a breakdown, to make it less likely: oil changes, filter replacement, greasing, checks on hoses, brakes and safety devices. It is the opposite of corrective (or reactive) maintenance, which repairs after the breakdown.

The preventive maintenance plan is the tool that organises it. For each machine, it answers four questions: which task? at what interval? who handles it? when was it last done? Without a written plan, preventive maintenance depends on everyone’s memory, and it ends up slipping into corrective work.

Scheduled, condition-based, predictive: the three ways to trigger maintenance

There are generally three types of preventive maintenance, depending on what triggers the task. In an equipment fleet, the first two are most often combined.

TypeWhat triggers the taskExample on a machine
ScheduledA fixed interval, in operating hours or time, regardless of apparent conditionOil and filter change at the intervals set by the manufacturer’s manual
Condition-basedThe observed condition of the machine: wear, leak, noise, a measurement exceeding a thresholdReplacing a hose after a leak reported during the morning check
Forecast or predictiveA trend measured over time, which lets you predict degradationTracking the trend of a measurement (oil analysis, sensors) to schedule the task

How to build your plan in 6 steps

  1. List all your equipment with its fleet number, category, make and model.
  2. Open the manual for each model and note the maintenance tasks and their intervals (in hours, in months, or both). The manual is the reference, not a general rule.
  3. Choose the trigger for each task: hours, calendar, or whichever comes first.
  4. Note when each task was last done (meter reading and date). If you don’t know, do it now and start from there.
  5. Assign who does what: in-house mechanic, dealer, rental company.
  6. Take regular meter readings and review the plan every week to prepare the workshop’s work.

Example plan for a small equipment fleet

Here is what a plan looks like once filled in. The intervals below are presentation examples: always replace them with those from your own equipment’s manual, which vary by manufacturer, model and working conditions. Regulatory inspections, such as VGP, are listed separately: they are not part of maintenance and are carried out by a qualified person.

EquipmentTaskTriggerInterval (example)Who
Mini excavator PEL-01Pre-shift check (fluid levels, leaks, tracks)CalendarEvery day of useOperator
Mini excavator PEL-01Greasing jointsHoursPer the manualOperator
Mini excavator PEL-01Engine oil and filter changeHoursE.g. 250 h or 500 h, per the manualMechanic
MEWP NAC-02Visual round and safety device testCalendarEvery shift startOperator
MEWP NAC-02Periodic upkeep (fluids, filters, wear)Hours or calendarPer the manualMechanic
MEWP NAC-02VGP (regulatory inspection)Calendar6 months for a MEWP (French ministerial order of 1 March 2004)Qualified person
Telehandler TEL-03Tyres, boom, stabilisers, hosesCalendarFrequent visual checkOperator
Telehandler TEL-03Greasing, fluids, filtersHoursPer the manualMechanic

The free Excel template: how it works

Our “preventive maintenance plan” template opens in Excel, LibreOffice or Google Sheets. One row corresponds to one task on one machine. You fill in the white columns; the green columns calculate themselves.

For each row, you choose the trigger (hours, calendar or both), the interval, the meter reading and date of the last time it was done, then the current meter reading. The sheet calculates the next due date in hours and date, the hours and days remaining, and shows the status: overdue in red, due soon in orange, up to date in green. A filter on the “Status” column gives you the week’s work list.

  • Free, no sign-up, free to edit.
  • Three example rows to delete to get started.
  • An “Instructions” tab in English.

When the spreadsheet is no longer enough

An Excel spreadsheet works well as long as one person keeps it up to date. It shows its limits once several mechanics are involved, once meter readings are taken on site, or once you need to keep proof of every job.

Trackary applies the same logic in a shared tool: a record per machine with its hour meter, maintenance and inspection due dates, field anomalies reported with photos, technician job scheduling and a maintenance logbook. Technicians close out their jobs from the mobile app, even without a connection, and the job report joins the machine’s history. Trackary does not carry out VGP inspections and does not replace the manufacturer’s manual. It does not handle invoicing, parts stock or GPS.

To go further on day-to-day organisation, read our guide to preventive maintenance for heavy equipment.

Is your maintenance plan stuck in an Excel file that only you keep up to date? Trackary shares it with your mechanics and alerts you before every due date. Request a demo →

Frequently asked questions

How do I run good preventive maintenance?

Write a plan per machine based on the manufacturer’s manual, take meter readings regularly, have the operator carry out a pre-shift check, deal quickly with reported anomalies, and log every job in the maintenance logbook.

Is preventive maintenance mandatory?

The French Labour Code requires that work equipment be maintained in a way that preserves workers’ health and safety (Article L4321-1). For lifting appliances, a maintenance logbook must be kept (French ministerial order of 2 March 2004). A preventive plan is the simplest way to meet these obligations.

What is the difference between scheduled and condition-based preventive maintenance?

Scheduled maintenance happens at a fixed interval (hours or months), regardless of the machine’s condition. Condition-based maintenance is triggered by observed condition: wear, a leak, a measurement exceeding a threshold.

What is predictive maintenance?

It is condition-based maintenance that relies on measurements tracked over time to predict when a part will degrade, and to schedule the task just before that point.

How do I build a preventive maintenance plan in Excel?

One row per task and per machine, with the trigger, the interval, the last time it was done and the current meter reading. Formulas calculate the next due date and the status. Our free template already does this for you.